Case Study
How an interim treatment system is becoming the foundation of a long-term carbon reactivation pool
1 year – Ahead of the first permanent PFAS facility
200M+ – Gallons of drinking water treated in year one
40,000 lb – NSF-certified GAC in service
Background
A regional authority with permanent PFAS treatment on the way
Perkasie Regional Authority is a Pennsylvania drinking water utility with a permanent PFAS treatment facility moving through design and construction. Rather than wait for that facility to come online, the Authority chose to start treatment immediately and run it in parallel with its larger capital project.
The Authority has a dedicated staff of 12 employees who work around the clock to ensure the safe supply of drinking water to it’s customers and adequate supply of water for use in fire emergencies. They provide both water and sewer services to multiple townships in Bucks County, PA and have over 8,000 combined customer connections.
Approach
Treat now, build in parallel
Running temporary treatment alongside the capital program pulled the Authority’s PFAS compliance schedule forward and delivered treated water to customers while permanent improvements moved through design and construction. That parallel strategy shaped the work from day one. Sentinel planned the interim installation and the permanent program as one plan, so the investment in temporary treatment would keep working after the permanent facility opened.
Solution
Rental GAC, fully integrated with existing infrastructure
Sentinel supplied a complete temporary treatment package matched to the Authority’s existing system:
- Four rental GAC vessels, each pre-loaded with approximately 10,000 pounds of NSF-certified granular activated carbon (GAC)
- An automated booster pump skid to maintain flow through the treatment train
- Pressure-control improvements that let the rental equipment tie in cleanly with existing system hydraulics
Pre-loaded vessels and a turnkey integration package kept deployment fast, so treatment could start well before permanent construction wrapped up.
“Reaching 200 million gallons is an important milestone, but the bigger success is that the interim solution is becoming part of the permanent solution.”
Andrew Strassner, President, Sentinel Water Solutions
Results
One year, 200 million gallons, and a carbon inventory in the making
In its first year of operation, the system treated more than 200 million gallons of water, an average of over half a million gallons per day. PFAS treatment began one year ahead of completion of the Authority’s first permanent facility, and customers received treated water throughout design and construction.
The GAC operating in the rental system is planned to form the foundation of the Authority’s own custom reactivation pool, supported by Sentinel’s NSF-certified reactivation and GAC inventory management services. At each change-out, spent GAC is reactivated for reuse and added to an inventory of Authority-owned media that can ultimately be placed into service at the permanent facility.
This lifecycle approach reduces reliance on virgin carbon and turns a one-time interim cost into a long-term Authority asset, offering a proven model for any drinking water system working toward a PFAS compliance deadline.